PP/DS : Change Requirement date in rrp3

3 days ago


avatar image


We have Created/Released production orders. We would like to change and 'lock' the required date to a date the planner desires. The date entered can be any date from current date to a future date. But the current behavior, is on entering the desired date heuristic kicks in and the entered date is replaced by a calculated date. Is there a way to enter a manual required date and lock that in. We do not want the lower level supplies required date to change based on entered date.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers