Hello Everyone,

I have a requirement where in I need to trigger the goods issue of the sales order item linked to the network header when a milestone is triggered through network activity confirmation. Any idea how this can be achieved through milestone functions or some other ways?

Thanks in advance.

Nithin.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Nithin,

When a milestone is reached, you will enter the actual date of completion of that milestone in CJ20N. As soon as you put that and save it, the block will be released in the sales order and you can post a delivery and a goods issue for the items whose milestone block was released.

Former Member
0 Kudos

Hello Robin,

Thanks for the reply. However, I will have more than one milestones spanned across multiple networks which will then be multiple lines in my billing plan.

For Eg

Milestone 1 : Electrical Diagram Network 1

Milestone 2: Goods Issue Network 2

Milestone 3: Final Payment Network 2

Sales order

123456/10

Sales order billing plan here will have 3 lines. And I would prefer to trigger the delivery of the sales order item only if the

"Goods Issue" Milestone (Milestone 2) is triggerred and not for the remaining two. Now how can I achieve that?

Hope it is clear

Looking forward to the answer

Thanks in Advance.

Nithin.

Former Member
0 Kudos

That is right Nithin. So when you have a milestone with the corresponding WBS in CJ20N done, put in the actual date of completion in CJ20n and save. What this will do is that for that item to which this Milestone2 network/WBS has been assigned will get cleared from the block and hence we can clear those items for delivery.

These blaocks you can assign in the network template in the activities.

Former Member
0 Kudos

Hi Nitin,

In the Billing plan of the SO please attach the Milestone No 2 for which you want to trigger further process.

Once you confirm the Milestone 2 in CJ20N, the block gets lifted in the SO. This will enable you to proceed further.

Hope this helps.