cancel
Showing results for 
Search instead for 
Did you mean: 

change of batch number

Former Member
0 Kudos

dear all,

by any chance can i change the batch number once material doc is posted and material is already there in stock with X batch number.

i dont want to cancel the material document.

please advice..

regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Create the new batch first through MSC1N for material, plant & sloc combination.

Then you can transfer the stock from existing X Batch to new Y Batch through 309 or 311 movement type.

Enter the receiving batch as the new Y batch. & the existing batch as X.

Edited by: Komal Gala on Aug 8, 2008 4:09 PM

Answers (1)

Answers (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

First create batch manually for material, plant and sto. loc. combination in MSC1N

Do Transfer Posting of Material from 1 batch to another.

Do 311 - Transfer Posting S loc to S loc in MB1B

Enter receiving batch as different batch