on 08-07-2008 1:33 PM
Dear SAP Friends,
While taking MRP run,the requirement were generated without considering the stock at Sub-contractor.
As we send the same material for machining operation at 2-3 sub contracors.
We take MRP run through the MD01(as scope of planning setting are here)
All 3 plants were take under the planning scope( X ).
No MRP area defined separetly.
Make to stock scenario here.
What customisation setting we will required to consider the subjected matter.
Please guide,& reply soon.
Regards,
Chandra.
Dear Chandra,
Special stocks are not considered for MRP run. Subcontracting stock is a special stock(O), hence is not considered for MRP.
Hope clear to you.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can have a separate dummy plant as subcontractor where the stocks will be stored ( that will be as Subcontractor stock).
U can include that plant in ur MRP RUN.
Regards,
Prakash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.