Budget control at top level Wbs

Dear PS experts,

we have a requirement to have budgets distributed from top level wbs to level 2 wbs and all transactions to happen at level 2 wbs, but only budget availability check to happen at top level. can you please let us know if this can be aceived.

Thanks a lot.

Regards,

Veera

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Aug 06, 2008 at 05:06 PM

    Try this:

    Exclude the level 2 WBS elements from the availability control by creating a user status profile (i.e., availability control business transaction is not allowed) and assigining the status to all WBS elements except your top level.

    Please search the forum if you need help on creating the user profile for Object Type WBS (T code OK02).

    Regards

    Sreenivas

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 13, 2010 at 09:29 PM

    hi Veera:

    I am trying to do something similar to this. Were you able to achieve a resolution to this requirement?

    Thanks