Interoperation time

Hi,

I have maintained interoperation time in routing.At the time of scheduling of orders it is not considering the time given.

How does move ,queue,wait time work in sap

thanks

sri

Edited by: Sri on Aug 6, 2008 3:03 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Aug 07, 2008 at 01:04 PM

    hi,

    When you assinged the the interoperation time? before order creation or after order creation? If is after order creation you have to do the Read PP master data.

    Another method is you can assing the interoperation time in the production order directly and click the rescheduling button.

    regards

    Mohan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.