We have created a PPM Project from Portfolio item. Then a PS project is created from PPM Project using accounting integration (Flag for transfer option)

We plan budget on portfolio item and display actual cost from PS on portfolio item too. However to do this, I have to manually add PS project definition link into portfolio item.

Is there a configuration which we can use to do this automatically?

Thank you in advance!

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Judith Gabriel
Mar 19 at 01:55 PM
0

Dear Mahendra,

The object link which is created in the Item to the PS-Project must be created manually.