COPA ML Data Flow Issue

0 Kudos

We have done migration from standard cost to actual costing material ledger in ECC6.The revaluated amount for cost component structure is not correctly showing for Activity cost and overhead expenses from ke27 to ke24/ke30.All the variance amount is cummulated in consumption value field only.As per standard configuration costing key created and assign to kepc with valuation level 2 and subsequently assign to material type.

KE27 log is showing following error-For actual data, value fields that were already populated before CO-PA valuation cannot be changed in valuation.

    1. As a rule, value fields that were filled before
CO-PA valuation - be it from SD or by a manual entry of a line item - can only be changed by means of user exits.
(Note that for plan data, CO-PA valuation always has priority over the values planned manually.)
    2. The valuation steps in a
CO-PA valuation strategy are numbered sequentially. These numbers determine the order in which the steps are carried out within that strategy. As a rule, value fields populated in one step can be used as a basis for calculating values for other value fields in a subsequent step.
    Value fields that were populated in a previous step are generally
not overwritten by subsequent steps.
    The exception to this are steps that use a CO-PA user exit. User exits let you change individual value fields.
    3. If you valuate using multiple
material cost estimates simultaneously, this means that the values of different cost components within the same cost estimate are aggregated and then entered in one CO-PA value field. However, value fields that already contain data from a previous cost estimate are not overwritten by a later cost estimate. Consequently, you should assign value fields in Customizing so that the values of different cost estimates are entered in different sets of value fields.

4. When condition values are transferred to CO-PA value fields, note that condition types that are assigned to the same value field are added together. This is also the case when the condition types come from different costing sheets within the valuation strategy.

And also showing ke/831 error for cost component.

Please help in identifying the issue.

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Look at 2453933,2456771,1671589 notes. May be it solves your problem.