HOW TO FORCE PROCESS ORDERS IN CNF STATUS IF ALREADY TECO

Hello Teachers.

I just want to ask if there is a TCODE that can FORCE TECO Process Orders (PO) to have a CNF status coming from a PCNF status?

Your comments will be much appreciated.

Thanks!

pcnf.jpg (10.0 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Mar 11 at 04:52 AM

    we use system status PCNF settings to restrict the TECO using code BS22