Changes made to Factory Calendar not working

Mar 09 at 10:14 PM

29

avatar image
Former Member

Hi,

I have recently updated Factory Calendar and set Saturday as workday, however daily background job is not picking Saturday as workday. After finishing Friday job the system is scheduling the job for Monday and skipping Saturday (which is now set as Workday in Factory Calendar). Does someone know what might be missing?

Thanks

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Martin Winn Apr 11 at 08:59 AM
0

Can you see your changes in SCAL?

Since we migrated to a higher netweaver version we have to reset the buffer every time we transport a factory change. In SCAL go to "Extras" --> "Update Calendar Buffers". This will refresh the buffer even a system message will be displayed.