Hi all,

We are on SRM 5 with extende scenario and i want to transfer PRs and Bid related to from non SAP-legacy.

I will use bapi BBP_PD_SC_CREATE_EXTERNAL and BBP_PD_BID_CREATE to create SC and Bid in a z program .

So my question is : in wich order have to create bid and SC, BID before or SC ?

Cheers,

Mustapha

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi all,

Can any body help please.

Im trying to test bpi "BBP_PD_SC_CREATE_EXTERNAL" and i have some errors :

00000 I Product could not be copied

00000 E 008 Error calling META BAPI META_CALCULATE_TAX

00000 E 013 Not possible to calculate tax

00000 E 020 Error occurred calling META_BAPI_DISPATCH

00000 E 034 S:ZMHF:034

00000 E 022 S:ZMHF:022

00000 E 011 S:ZMHF:011

00000 E 010 S:ZMHF:010

00000 E 007 S:ZMHF:007

00000 E 005 S:ZMHF:005

00000 E 004 S:ZMHF:004

00000 E 003 S:ZMHF:003

00000 E 002 S:ZMHF:002

00000 E 001 S:ZMHF:001

00000 E 540 System TAZZTG310 of purch. organization DIRECTION DES ACHATS differs from doc. reference TAEDTH310

00000 E 247 Plant for follow-on document missing

00000 E 008 No account assignment exists. Enter an account assignment

00000 A 078 Enter the company code

00000 E 822 Error in account assignment for item 1

Former Member
0 Kudos

Hi,

I hope you know SRM sourcing flow goes like this :

SC --> Bid invitation --> Bid --> Contract/Purchase order --> Conf --> Invoice.

Best regards,

Sridhar.