Hi,

For a given Budget Change Line Item (table FMBDP) we need to find the Budget Header (FMBH) to which it belongs to.

Does anyone knows how to do it?

Thanks,

Gabriel

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Eli Klovski
Mar 12 at 12:17 PM
0

Hi,

It's a combination of reference document (REFDOCNR) and original application (TECHORG_9). If the original application is budget entry (BWB), i.e. operation done via FMBB and not by some internal process, e.g. carry-forward, then the reference document will be the one which you see in FMBH.

Regards,

Eli

Show 4 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Eli,

Thanks for your help. In the system I'm working at, most of the Change Line Items have Reference Document Number (REFDOCNR) with value "1". Can this be caused by the Original Application you mentioned?

Thanks,

Julian

0

What is the value in TECHORG_9 field (last field of the table)?

0
Former Member
Eli Klovski

The value is "BAPI-ED".

Thanks!

0

So, these are documents not directly introduced, but via BAPI.

But, still, it doesn't matter. The reference document (REFDOCNR) should be the one introduced in FMBH even in this case.