Hi gurus,

is there any way of printing a date onto the PO-printout that differs from the document date?

E.g. PO is created on Aug 5, 2008. So, the document date is (and has to be!) Aug 5, 2008. But the date on the printed order document should be e.g. Aug 10, 2008.

Can this be achieved without modification?

Thanks in advance

Alicia

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

The form is always your personal form, it has the logo of your company etc etc.

So you can forsee to print anything you want.

former_member504446
Participant
0 Kudos

Ok, thank you all. I doubted anyway that this could be done without modification.

Thanks

Alicia

PS @ Kedar: You don't even want to know... Got something to do with outline agreements.

Answers (2)

Answers (2)

Former Member
0 Kudos

this is not achievable without modifying program.

but why you want different date on PO print?

pankaj_singh9
Active Contributor
0 Kudos

Hi,

It is not possible w/o ABAP help or w/o program modification.

You can use any field at Header Level in PO to maintain this date and print it in PO by making changes in PO Print layout (Smartform or SAPScript)

For e.g. you can use field Validity start under "Additional Data" tab.