hi

Reorder Point Planning : briefly - typically there are many more things to consider and set but this may get you started:

Material Master data: MRP1 view

Assign a reorder type MRP type, i.e. VB, V1 (there are a few standard ones). Lot size = HB. Specify a reorder point and maximum stock level.

If you create a new MRP type you can set forecasting for optional or mandatory in the IMG.

Historical consumption values can be entered in the consumption tab in material master - additional data or branch from forecasting tab.

check this

http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d256344af11d182b40000e829fbfe/frameset.htm

http://www.sap123.com/showthread.php?t=89

for manual reordering point

and

http://www.sapfans.com/forums/viewtopic.php?t=263729

for automatic

regards

kunal

Edited by: kunal ingale on Aug 5, 2008 1:00 PM

Former Member
0 Kudos

Hi

Thanks for your reply. I went through the links that you gave me. For automatic reorder point only concept is given. There are no tcodes. Can you please provide me with tcodes for me to proceed with this

Thanks

Subhash

pankaj_singh9
Active Contributor
0 Kudos

Hi,

1. MM02 - MRP 1 view, here enter MRP Type - VM, Lot Size - EX and then enter Quantity for Reorder Point generation and in Consumption tab add / put all consumption historical values...

2. MD02 - MRP Run for Material with following Parameters

Material

Plant

Processing key NETCH Net change for total horizon

Create purchase req. 1 Purchase requisitions

Delivery schedules 3 Schedule lines

Create MRP list 1 MRP list

Planning mode 3 Delete and recreate planning data

Scheduling 1 Basic dates will be determined for plann

Activate all "Process Control Parameters"

And then Press Enter.

System will give Planned Order/Purchase Req. if Stock of Material falls below the Reorder Point.

Also put some stock for the material so that you can analyze it in better way.

3. MD04 - Stock Requirement Analysis

Note: -

For Lot Size FX, you need to maintain "Fixed lot size" also in MRP 1 view.

And the calculation will happen as following;

Fixed lot size = 500 EA

Reorder Point = 1000 EA

Available Stock = 700 EA

Now as per calculation requirement is of 300 EA (Reorder Point - Available Stock = 1000 - 700 = 300 EA)

But Planned Order or PR will be generated of 500 EA since Fixed lot size = 500 EA.

But in case of Lot Size "EX", system will generate a Planned Order or PR of 300 EA only.

And Use Transaction Code MDBT for Planning in Background

former_member581212
Active Contributor
0 Kudos

Go to MM02 - > ChangeMode of your material for which you wanna maintain the MRP -> In MRP tabs -> Fill the data like Reorder point, safety stock, in Consumption tab add / put all consumption historical values...

THIS IS THE BIGGEST PREREQUISITE FOR THE SAME..

From other tcodes you can display the reqirements as usual..

Regards,

Priyanka.P

AWARD IF HELPFULL