on 08-05-2008 7:23 AM
Hi all,
i have a scenario where in two company codes are there ,
i want to carry out the Intra Company STO between the plants and Inter Compy STO also.
For this i want to know from start to end of customizing and transactions to progress this scenario...
please help...
Hi,
1.customization settings for INTER-company STO(with SD & WITH BILLING)(Doc.type:NB, item category: blank/std.)(both plants are in the different company codes)
Customization settings for MM Side:
path: spro->materials mgmt.->purchasing->purchase order->setup stock transport order
*define shipping data for both plants (supplying plant & receiving plant)
define & create checking rule
*assign delivery type&checking rule to the supplying plant
assign doc.type to the both plants
assign customer to the receiving plant(customer A/C group:sold-to-party)
End user side:
material master record must be maintained in both plants.
during creation of MMrecord , u have to select sales orgn.1 &2 views.
*create PO (ME21N)withdoc.type:NB,Item category:blank/std.
shipping tab appears in the item details
*create outbound delivery(VL04/VL10G) against PO
create outgoing invoice(VF01)
*create PGI(post goods issue)(VL02N)using movement type:643
*INCOMING invoice(MIRO)
*GR against PO(MIGO) using movement type : 101
THIS IS the entire step-by-step process for INTER company STO.
I think this info.useful for u.
reward me
bye
Narasimha Rao G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1.customization settings for Intra-company STO(with SD & WITHOUT BILLING)(Doc.type:UB, item category: U)(both plants are in the same company code)
Customization settings for MM Side:
path: spro->materials mgmt.->purchasing->purchase order->setup stock transport order
*define shipping data for both plants (supplying plant & receiving plant)
define & create checking rule
*assign delivery type&checking rule to the supplying plant
assign doc.type to the both plants
assign customer to the receiving plant(customer A/C group:sold-to-party)
End user side:
material master record must be maintained in both plants.
during creation of MMrecord , u have to select sales orgn.1 &2 views.
*create PO (ME21N)withdoc.type:UB,Item category:U
shipping tab appears in the item details
*create outbound delivery(VL04/VL10G) against PO
create PGI(post goods issue)(VL02N)using movement type:641
GR against PO(MIGO) using movement type : 101
THIS IS the entire step-by-step process for INTRA company STO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please go to below link
http://help.sap.com/bp_bblibrary/600/BBlibrary_start.htm
and select country as INDIA
Find J51,J52,J53
relates to INTRA and INTER STO
Thanks & Regards
Swathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
For intra Company code.
1. maintain internal vendor and customer for both the plant for which STO is created.
2. make sto using me21n
3.make delivery vl10b
4 do PGi vl02n.
5. goods receipt- migo
6. miro of freight.
Regards,
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
http://www.sap-img.com/sap-sd/configure-intercompany-stock-transport-order.htm
Go through the link..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.