Configuring Half Day in SAP

Former Member
0 Kudos

Dear All,

My Client is having a requirement which is as follows:

He is having a factory and he wants to declare Saturaday as half day and Sunday as Holiday. We all know that we can declare a full day Holiday in Factory Calender.

But, how can we declare half day holiday (or Number of Hours for Saturday) in Factory Calender. The client will not do any transactions after half day holiday.

Can any one through a light on this?

Thanks,

Prakash

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

At which SAP process do you need to know that the Saturday is just a half working day?

one that comes in my mind is the capacity and shift planning in production.

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

menu path:time magt>work schedule>daily work schedule--

>define rules for variants.

in the screen define rules for variants:under the

coloum 'holiday class' u'll put a 'x' under '2' that

denotes half day in sap...nw lets say in ur co. only sunday

is weekly off and public holiday can fall on any day of the

week so under the iii coloumn i.e 'weekdays'u'll put a 'x'

under all the days ecxcept sunday....nw under second

coloumn i.e'holiday class nxt day u'll put 'x' under all

the holiday classes....

secondly, u'll come to screen: define daily work schedule

where u'll make a description of half day by taking 4 or 5

hrs half day n there under DWS VARIANT U'LL put the rule

created under screen rules of variant....

n then while making PWS i.e period work schedule u'll hv to

show sat as half day as sunday is weekly off in ur co.

and once u'll create PWS MANNUALLY THERE U'LL PUT THE RULE

OF HALF DAY BEFORE EACH PUBLIC HOLIDAY MANNUALLY....

PLS CORRECT ME IF I'M WRONG.THANX

Thanks & Regards

Swathi

Former Member
0 Kudos

Hi

Thanks for the reply,

I am still not understanding the configuration in detail. Can you please provide the step by step configuration? Also, can you please tell me where this rules are assigned -- is it to Factory Celender?

Thanks,

Prakash