Hi,

I gone through all available threads, not got any relevant answer.

Settings I have done:

1. Tolerance limit defined - 100% (transaction group -01, purchase order)

2, Budget Profile maintained.

3. Budget Availability check activated.

Although, system is not going through the budget check when budget exceeds. means system allows to create PO in case budget exceeds.

Regards,

MM

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Ken Melching
Mar 10 at 01:12 AM
0

Provide screenshots of your Budget Profile configuration.

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Mar 12 at 05:46 AM
0
Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi,

Try to uncheck the Releases and Check the Budget again.

Create new network or activity and check it

Regards

Terence

0

Please provide what steps you have taken to troubleshoot this issue. And how the PO was created, etc.

What is the tolerance configuration settings?

Also please search for budget related issues. There have been many forum entries regarding budgeting.