on 08-05-2008 4:35 AM
Hi gurus,
may i know how planned cost in production oder is being generated and in table COSS or COSP, what are the criterions that the system will considered before it determines which period will the planned cost be posted to?
Thanks in advance.
Regards
Yiming
Planned cost for a production/planned order is determined based on the cost of the raw materials and on the activity cost.
In material master we will define the cost of the material.In BOM we will define how much qty of components/rawmaterial is required for making the header material.Based on thisraw material cost for making an item will be calculated
In routing we will define how much power,labour etc required for making an item.In KP26 we can maintain cost on a monthly basis.Based on this cost system will calculate the activity cost.
I think now it is clear
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Planned cost u can see in table S027. And regarding posting of planned cost to period is the way u run cost estimation. But u are thinking the update the planned cost from production order then it is not possible. The production order shows the planned cost based on the quantity structure.
Hope u got the answer
Thanks & regds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.