Hi Gurus,
I have a Process Order with 3 Phases (0020,0040,0060). I confirmed 0020 and 0040 partially by 50%. But then im trying to confirm 0060 with more than 50% of the quantity but the system is not allowing me to do so. How can i configure in such a way i can confirm quantities more than the previous ones?
Many thanks,
Kumar
Hi
You can check the sequence of the operation confirmation in IMG - Define Confirmation Parameters.
Try and see it work for you and what you wanted.
dannysao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Kumar
I think IMG at Confirmation, u have maintained both (UnderDelivery & Overdelivery) tolerance limit with Error when Quantity falls below tolerance limit.
You have to maintained tolerance in not checked.
I think this will reslove your problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.