Hy Experts,
we are facing a problem while stting up CHARM in a three system landscape:
The error occurs wile attempting to create an IMG project:
-
Longtext:
Status values are different in source and target systems. See long text
Message no. SOLAR_SPROJECT022
Diagnosis
When you create a customzing project in the component system, the Solution Manager project status values are copied. If these values do not yet exist in the component system, they are created. If they already exist, they are not changed.
In this case, the copied status values exist in the component system, but they may have a different meaning: their descriptions differ.
Procedure
Check the meaning of the status values and make them match. If this is not possible, create and use new status values to avoid inconsistencies.
-
How can I check and change this settings in component systems?
kind regards
T. Uhl