Assigning budget profile to already existing project

Hi All,

Please suggest how can we assign budget profile to already existing project .

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Aug 04, 2008 at 10:34 AM

    Hi Vishal,

    You can go the Project builder, open the particular project and in the detail screen of the project definition, enter the budget profile in the control data tab page.

    Or goto SPRO->Project system->Costs->Budget->Stipulate default budget profile for Project definition and assing the bedget profile.

    Or enter the Budget profile in the Controlling tab page of the Project profile.

    You can do all these for existing projects.

    regards

    Pratap.V