Hello all,

My querry is whether hierarcy level of a WBS element can be changed ,say from 3 to 2... if the budget is already assigned to that WBS.?

because in my project..whn i tried the same..it gives the error " budget already assigned to the WBS so no change to the structure can be made".

Please let me know the solution , if its possible to modify

Thanks in advance

regards

Sandeep.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 04, 2008 at 08:49 AM

    Standard SAP does not support the same, once budget is assigned. if possible change the description to suit ur requireemnt.

    regards

    Murali

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Murali,

      The error is " you cannot change structure since budget is assigned to it "

      So i tried to remove budget using cj30 also tried returing through cj38. but nothing unfortunately wrked.

      As you suggested ..i also tried to run opsx for that particular wbs...but again no results 😔

      Any other suggestions 😊

      Thanks and regards

      Sandeep