budget profile error

While creating budget through CJ30 for a project , the following Error message comes

"Assign plan/ budget profile to the object"

Although in the config. Budget profile is already assigned to that Project profile.

But through CJ02 ,in the control screen, the Budget profile field shows Blank for that project.

Please suggest solution as soon as possible.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 04, 2008 at 08:25 AM

    Assign Budget to profile in your project manually and continue. It will work.

    regards

    Pratap.V

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 05, 2008 at 05:36 AM

    HI

    Enter the budget profile in the T-code Cj20n or Cj02 mannually save it & continue.

    It must be taken automaticaly when u select the Project profile, if it is not taken enter mannually & save it.

    Regards

    Raman T S