Aug 04, 2008 at 07:17 AM

MRP Run problem

33 Views

Hi All,

I have a problem during MRP run.

I have entered PIR for the Fininshed product on 08.08.2008.

The FG is having 10 levels of BOM lower to that.

After running MRP, the planning results are like this,

Planned order created for FG on 11.08.2008.

The planned order for the next level material is created on 12.08.2008.

( DepReq of FG 12.08.2008 is also showing wrong here)

The planned order the second level BOM is on 13.08.2008... and so on..

For the lowest level BOM material it is giving the Planned order date 18.08.2008

For inhouse produced material as well as externally procured material it is adding one day at each level of BOM.

I want the material on 08.08.2008 but the system planning the reverse...

The system is not giving Reschduling date also.

Please give me solution for this problem.. why it is happening like this?

Thanks & Regards

Bala