Dear All,

What is the way by which Opening Job In Progress is done in SAP Business One. The situation is that in the legacy system and in the closing Balance Sheet there is value for Job in Progress and now we want to put into SAP as Opening Job in Progress with effect in Finished Goods inventory and with effect in the Financial.

Looking forward for an positive solution for all.

Thanks and Regards,

Kawish Junaid Mazhari

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member583013
Active Contributor
0 Kudos

The Work in progress account is affected when you create a Issue to Production.

Typically, the Inventory Raw Materials / Inventory account is credited and the Inventory - WIP (work in progress) account is debited.

You could probably import the transaction as Production Orders and process an Issue to Production.

Suda

Former Member
0 Kudos

Hi

It is called work in progress in SAP Business One and that is having account. you can put it there

Ashish Gupte