Hi QM Consultants
Kindly provide me the list of steps to perform the Automatic UD for the 01 inspection type
Regards
Deepak Goura
Hi Deepak,
- Tick the check box "Automatic UD" in the inspection set up for the inspection type 01, at material master level or at configuration level.
- It is better if you create a separate UD code (QS41) and attach it to the Selected Set. (QS51)
- These two are the main prerequisites for Automatic UD, do this settings and let me know if don't work.
Regards,
Shyamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepak,
Back ground schedule run for automatic usage decision using QA17.
with refe to the tcode QA19.
Thanks & Regards,
Babusingh.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check out T code QA10 and check have you maintained automatic usage decision in material master for that inspection lot origin
Regards
Pravin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.