on 08-02-2008 7:24 AM
Thou all the activities under a WBS are confirmed, WBS actual dates are not populated automatically. Any setting is missing?
Thanks
Scenarios
1 WBS without activities
1.1 Actual start date : should be maunally entered if the WBS, if the status is atleast "Partially Released"
1.2 Actual finish date : should be maunally entered.
2 WBS with activities
2.1 Actual start date: will be automatically populated for the activity confirmations or by the function, Edit > Reconcile dates > Determine actual dates.
2.2 Actual finish date : should be manually determined in project planning board by the function Edit > Reconcile dates > Determine actual dates.
regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sachin,
Have a look at the following link also.
http://help.sap.com/saphelp_46c/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm
regards
Pratap.V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sachin,
The answer to your question is available in the below link.
https://www.sdn.sap.com/irj/sdn/forums
regards
Pratap.V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.