WBS Actual Dates

Former Member
0 Kudos

Thou all the activities under a WBS are confirmed, WBS actual dates are not populated automatically. Any setting is missing?

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Scenarios

1 WBS without activities

1.1 Actual start date : should be maunally entered if the WBS, if the status is atleast "Partially Released"

1.2 Actual finish date : should be maunally entered.

2 WBS with activities

2.1 Actual start date: will be automatically populated for the activity confirmations or by the function, Edit > Reconcile dates > Determine actual dates.

2.2 Actual finish date : should be manually determined in project planning board by the function Edit > Reconcile dates > Determine actual dates.

regards

Murali

Former Member
0 Kudos

Murali,

in responce to 2.1 & 2.2 u say that "_Actual start date: will be automatically populated for the activity confirmations_". Why it not happening in my system thou I fully confirm all the activites under a WBS. I assume it is standard behaviour in SAP.

Thanks,

Former Member
0 Kudos

check the WBS & network scheduling parameters defined for the project profile with which u have created the project. wether automatic dates scheduling is set or not. if not u have to do it manually.

regards

Murali

Former Member
0 Kudos

Hi Sachin,

Have a look at the following link also.

http://help.sap.com/saphelp_46c/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm

regards

Pratap.V

Former Member
0 Kudos

Hi Sachin,

The answer to your question is available in the below link.

https://www.sdn.sap.com/irj/sdn/forums

regards

Pratap.V

Former Member
0 Kudos

I could find anything in "https://www.sdn.sap.com/irj/sdn/forums" link. Send me the right link.

Thanks

Edited by: Sachin S on Aug 4, 2008 5:47 AM

Former Member
0 Kudos

Hi Sachin,

The second link will clarify your doubts.

regards

Pratap.V