Production order confirmation during CO15 transaction

Dear,

I am doing production order confirmation by CO15 ,My order is of 5 qty. i enter 2 yield ,2 scrap and 1 rework during confirmation.when i am doing good receipt for order system should allow me only good receipt of 3 qty ie 2 yield & 1 rework qty.But my problem is that system allowing me goods receipt of scrap qty confirmed,

logically it shouls not happen.

Can you give solution for above problem.Is there any setting or user exit available.

Reward points for useful answer

Regards,

vidyasagar

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 01, 2008 at 02:36 PM

    Hi Vidya sagar,

    Here you need to understand one thing,scrap which you declare in confirmation is just for information purpose,it doesnt mean that scrapped qty will be posted to scrap sloc or any movmnt will happen automatically,scar can be handled in diff ways,either GR all the qty & then from there do transfer posting scrap sloc or keep the material as negative qty in component overview-prod order & during auto GR this will also get posted

    Hope the above is understandable & clear

    Regards,

    SVP

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 01, 2008 at 03:05 PM

    Hi,

    If you want to good reciept for scrap then you need to maintain it BOM with -ve quantity after that system will allow you posting of scrab stock in inventory with 531 movement type.

    Please try and come back.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 01, 2008 at 03:10 PM

    Dear,

    I think you are confirming 2 yeild qty and doing the GR in MIGO/MB31.

    If so system will present the target qty from production order and not the confirmation qty from operation.

    If you are expecting that then you need to do GR during confirmation with control key for last operation which supports GR...in std sap system it is PP03/PI03.

    pl come back

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.