Consumption of material on activity confirmation.

Hello,

The requirement is that backflushed material should get consumed once activity has been confirmed.

But this is not happening since the system is unable to determine the valuation type of the material. Have checked the same in CN25 and Goods movement tab, valuation type is blank, the same needs to be entered manually.

Once valuation type is entered and saved, material is consumed.

The valuation type should be determined automatically.

We have already done the desired setting in stock determination group and assigned the same to movement type 281.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Aug 01, 2008 at 09:13 AM

    are you using special stock in your case

    shekhar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 01, 2008 at 09:32 AM

    Yes project stock (Q)

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Nidhi ,

      I felt your issue interesting as i never came across backflushing split valuated materials and could nt test in my system even 😊

      However you may refer to notes 331421 and 374707 which may be helpful to you .

      Cheers

      Kish

  • avatar image
    Former Member
    Aug 01, 2008 at 12:27 PM

    just a guess work...have you people maintained REPITITIVE MANUFACTURING profile in the MRP view of the material master?

    other thing is that in case of PP routings we can define in the control keys whether a milestone confirmation is required or not.this perhaps leads to automatic consumption.but with our PS the same is not possible.

    shekhar