on 08-01-2008 6:35 AM
while doing the confimation, system takes raw material qty on dev. & quality server is ok but in prod server qty of raw mat. takes more than required qty.why this is? what is the setting needed it?
regards,
narendra
Hi Narendra,
Please check BOM qty and Component scrap % and Operation scrap also check setting in Confirmations customization -OPK4 tranasaction.
You have to use user exit only to avoid it.
1.CONFPP02 - for checking good issue during confirmation
2.MBCF0002 - for Checking Confirmations during the Goods receipt.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Aug 1, 2008 11:18 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check any Assembly/Component Scrap is maintained??
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check whether have you assigned any Assembly scrap % in MRP1 view of material master or Component scrap % in MRP4 view.
Check in BOM have you assigned Component scrap % or Operation scrap %.
If so remove and check the results.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.