Hi,
Plant is not assigned to cost centre, but to company code. You can derive cost centre based on plant via substitution, for example.
Regards,
Eli
Hello,
Cost Centers are NOT assigned to Plants. (They are independent of plant).
Just for your information, plants are part of MM organization structure where as Cost centres are part of Controlling (CO-CCA).
Cost centers have a time frame where as plants no time frame.
Regards
Ambadas