Hi all,
Please explain to me after preparing a project plan, how to assign workforce and machine/ equipment for network or for an activty.
Thanks in advance
Hello,
After creating a project.
In transaction CJ20n
Edit- WBS element-Project team for WBS element.
After this select the people to be assigned and to the WBS element
Next step:
CMP2:
In the above transaction assign the people of Project team to different Network activities.
To assign material components.
CN33:
For this a BOM should be available in system with reference points. Respective reference points need to be assigned to activities in Project structure.
Else material components acan be directly assigned to Network activity in Project structure using CJ20n
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.