PS - Process flow

Hi all,

Please explain to me after preparing a project plan, how to assign workforce and machine/ equipment for network or for an activty.

Thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 01, 2008 at 05:24 AM

    Hello,

    After creating a project.

    In transaction CJ20n

    Edit- WBS element-Project team for WBS element.

    After this select the people to be assigned and to the WBS element

    Next step:

    CMP2:

    In the above transaction assign the people of Project team to different Network activities.

    To assign material components.

    CN33:

    For this a BOM should be available in system with reference points. Respective reference points need to be assigned to activities in Project structure.

    Else material components acan be directly assigned to Network activity in Project structure using CJ20n

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Nidhi / SAP guru

      Assigned project team to WBS element, when I am carring out workforce planning for network it is giving message "No requirements were found for the selection criteria" so what will be the problem?

      Thanks in advance

      Regards,

      Praveen