How to restrict user for changing the Budget profile

Hello,

we have a requirement like this

To restrict the user for changing the budget profile once the budgeting is done.

The Standard fictionally is not able to restrict user for changing the budget profile even after budget allocation, budget release and project release also.

please suggest any solution on this

Regards

Shiv

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 31, 2008 at 02:41 PM

    Hi,

    Create User Status and forbid the budget transaction.....Once u release the project assign this status to WBS.

    regards

    Abhinay

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 31, 2008 at 08:42 PM

    Hi,

    I would assume the initial budget profile in the project is default and the user doesnt input or change it while creating the project. If thats the case, then go to OPUJ and make the budget profile as display only. This will prevent the users from changing it.

    Thanks

    Jagdish

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 31, 2008 at 06:23 PM

    Hi Shiv:

    Additional to User Stat, you can block the status with the objet b_userstat.

    Regards