In a report, I must change the cost center for Purchase Requisition and Purchase Order.

In my opinion I must use the bapi: "BAPI_REQUISITION_CHANGE" and "BAPI_PO_CHANGE", but I don't know how to use.

Is this correct ?

If yes, can someone explain to me how to call them to change cost center ?

Thank you in advance.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 31, 2008 at 01:25 PM

    Hi

    Please refer the below link you may useful.

    BAPI_REQUISITION_CHANGE

    Thanks and regards,

    Syf

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 31, 2008 at 01:44 PM

    For PR you need to update cost center in field REQUISITION_ACCOUNT_NEW-COST_CTR

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.