Dear expert

I want to update COBRA information while create/edit WBS by T-code: CJ20N.
I found the following exit about WBS. But I don't know how to update COBRA in them.

BADI: WORKBREAKDOWN_UPDATE
Substitution(GGB1): Project System > WBS Element

Can anybody help me? Thanks a lot.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
avatar image
Former Member Mar 09 at 12:48 PM
0

I have found the answer. Than you!

https://wiki.scn.sap.com/wiki/x/JQbTH