Budget control during PO generation

18 Views

Dear Sir,

We make the PO against the Account Assignment . The Account Assignment is the WBS Element . We use Project System and mention the Budget against the WBS Eleement .

Sir , we desire that at the time of PO saving , System should check the Budget Balance and should not allow to save the PO incase it exceed the Budget Balance amount .

Kindly guide us as what steps are required to have this check pl .

Regards

B Mittal