Budget control during PO generation

Dear Sir,

We make the PO against the Account Assignment . The Account Assignment is the WBS Element . We use Project System and mention the Budget against the WBS Eleement .

Sir , we desire that at the time of PO saving , System should check the Budget Balance and should not allow to save the PO incase it exceed the Budget Balance amount .

Kindly guide us as what steps are required to have this check pl .

Regards

B Mittal

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jul 31, 2008 at 01:05 PM

    Hi

    If you have maintained the Budget in the WBS elemnt as per the Standard Process the Sytem will stop you to Create or Save the PO once Budget is exceeded.

    THis Check is already maintained in the System, Just ensure that Budgetary control is maintained for the PO.

    Thanks & Regards

    Kishore

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.