I Closed Maintenance plan in Feb one plan but March its not Scheduled after Feb completion. Directly its Scheduled for April direct March month its not triggered.

In IP10 i checked its showing Basic Start Date is Feb, Completed by March but I closed the actual plan in March 4th.

Can you please anyone help me out from this problem

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Suleyman Bulus Mar 07 at 01:10 PM
0

Can you provide screenshots of IP10 and scheduling parameters tab of the maintenance plan?