on 03-06-2018 1:07 PM
Hi EWM Gurus,
I am using HANA Embedded EWM 16/10. PPF action is activated. I am using VL31N t/code for EWM inbound process. Users do not check SMQ2 after, inbound delivery is created. When I get any error on QRFC Monitor. I want to show that message on VL31N screen and rollback all process. Is it possible ?
İf it is not I want to show error message or send e-mail if it gets error on QRFC.
Thanks in advance
Nuri Nihat Atasever
Hi Nuri,
"When I get any error on QRFC Monitor. I want to show that message on VL31N screen and rollback all process. Is it possible ?" :- As per my understanding, Data entered in VL31N first committed the Data Base, then it send to EWM using QRFC. I guess there is no option for automatic delete or rollback all process.However, you can do manually if you do not need that delivery to process further.
->First Delete the queue, then change distribution status, then delete inbound delivery.
"İf it is not I want to show error message or send e-mail if it gets error on QRFC"-> Please check the link https://archive.sap.com/discussions/thread/3823049
Kind Regards,
Ajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ajit,
Okey first option rollback and automatic delete is not possible as I understand.
When I get any error on QRFC, I could delete ınbound delivery as your suggestion.
For Second case " sending mail " I will check the link and let you know the situation.
Thank you for your answer.
Best Regards
Nuri Nihat Atasever
Hello Nuri,
Unfortunately it is impossible to inform the user in VL31N about the failed queue. But I have some good news for you:
Regards,
Katrin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.