I have to create a Delta process chain which involves 20 parallel data loading processes.

Which is the best way to approach this? How many parallel processes should i have to maximize the performance and efficiency of the system .

What is the recommended approach for Hana for Parallel Branches ?

Accepted Solutions (1)

Accepted Solutions (1)

KalyanDittakavi
Explorer
0 Kudos

That depends on the total nbr of Processes/ servers you have available at a given time.(of this data load) and also depends on what time you want to schedule this load? are there any other data loads happening at the same time.. in that case, you might want be very carefull not use entire back ground processes for this job alone..

Thanks

Kalyan