note:1530596 CKR1 should be avoided, how to solve "Material in plant has a released cost estimate"?

Hi export,

When I see the note:1530596, On this page has been displayed do not use CKR1. It's just for delete test data.

But currently, there are some material change BOM at 2018/03. When I re-costing run for these material. SAP feedback the message "Material oooooo in plant xxx has a released cost estimate"

How can I solve the CK11N error message "Material oooooo in plant xxx has a released cost estimate" problem?

What is the SAP standard re-costing run step?

Best regards,

Eric

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Mar 09 at 11:58 AM

    H.i ,

    As mention in the SAP Notes they have mention the following steps for resloution

    Enter transaction CHECK_ANCHOR.

    Uncheck the flag 'resolve inconsistencies'.

    Execute in test mode and check the result.

    If there's an inconsistency, activate flag 'resolve inconsistencies'.

    Execute in update mode. The error is no longer displayed in MM03 as the future price is now empty.

    Kinldy check if it is working or not