Skip to Content
avatar image
Former Member

Material Group based Detailed Scheduling in APO

Hi,

We have a requirement for which it is required to perform scheduling based on Material group.

Example:

We are having material A, B and C in material group "01" and E, D and F in material group "02".

Workcenters as X1, X2, and X3 can be used for any of material.

Now,

X1- ____A_______||_____B_______||

X2- ______C__________||_______C________||_______E________||

X3- ______E______||___________B______________||

If a new sales order is coming in for material "A", it is required that system will plan this on workcenter X1 as same group material is running on this line with keeping time constraint too.

Note: We can't fix work centers as each work center is able to produce any of material ( i.e. A, B, C, E, D and F)

How do map this in SAP APO-PPDS?

Regards,

Yogesh Singh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers