hi friends.

can anyone explain me how to activate serial numbers for components and finished product.

i.e.. i want to capture serial numbers during goos issue and gr for the finished product.

pls guide

thanks

jaya

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor

Hi Jaya,

You can assign componenets (with serial nos.) to assembly ( also with serial nos.) with COIB after goods receipt.( Menu path --Logistics -> Plant maintenance -> Management of technical objects -> Installed base -> Create (special) -> With reference to production data.)

Example: Say assembly sr. no. is 1

And components serial no. are- 1,5,10,20 and so on.

After assignment of components it can be viewed on right part of screen, You can have the assignment history--- ie for which assembly no. which components are assigned or vice versa. In production order i.e in descrete mfg. it can be directly done at the time of operation confirmation.

The following is the detail steps:

1. T code--COIB

2. Enter material code ( Assembly). You can select specific serial no. of assembly --- by putting sr. no. in serial no. field.

3. Click on list tree- you will find all assembly with serial numbers.

4. Click on explode-- it will show the BOM ( in bottom left corner of screen)

5. Select the assembly numbers for which you want to assign the componets

6. Clik on tranfer

7. Select the component

8. Also select the assembly no. on right side screen.

9. Select the serial no. which you want to assign to an assembly

10. Click on assign

11. You will find all the components will get assigned to assembly with serial numbers.

12. Now on right side screen there is "save" button. ( It will ask you create/ change as built in foreground or background?

13. Select as foreground

14. Save

15. You will find a message at the borttom --- saved.

16. Now you will find tick mark ( in front of finished material) in right part of screen ( indication of assignment of components)

Regards,

R.Brahmankar

Former Member
0 Kudos

hi brahmakar,

we did exactly what we u said. when i enter the assembly and its serial number and click on transfer everything is getting dissappeared. the assembly has components and those components are also serial numbered. now we want to assign component serial number to header assembly serial, n umbers to pick during delivery. vl01.

pls guide me further

thanks

jaya

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Jaya,

Thanks for your great reward,

Please go through this link.

[Serial number|http://help.sap.com/saphelp_46c/helpdata/en/dd/f8c817b3f911d1896e0000e8284931/frameset.htm]

Regards,

R.Brahmankar

Former Member
0 Kudos

dont worry too much about rewarding points. if u have true intentions to help the community the points will chase you automatically.when i actually followed your intructions the entered field values got dissappeared. now tell me how much i have to reward you. i have again rewarded you for the link. hope you are satisfied. if not let me know i will reward 10 points.

thanks

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Jaya,

Can anyone explain me how to activate serial numbers for components and finished product?

It was your question I have replyed to that with complate step.

I think you are missing any setting. Please check again and come back.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hello,

What you can also do is to create serial no profile under plant maintenance customizations may be one for the Components and another for the assembly and make it a mandatory in material master ...Serial no profile need to be assigned to both in Sales and workscheduling view.(for inhouse produxced part

)

Then system automatically asks for serial numbers during GI and GR

Regards.

Shashi

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Right Mr. Shashi,

These are the steps

1. Assign the serial number profile in corresponding material master

2.Create separate serial nos with tcode: IQ01

3.Upload the stock for corresponding material with Tcode:MB1C

While uploading itself it will ask for serial number ---> assign it

4.Then create the sales order. U can assign the serial number in delivery document also

Regards,

R.brahmanka

Former Member
0 Kudos

hi brahmakar,

now i am able to transfer the components with serial numbers. after transferring to the right hand side there there is one more save icon. when i click on that it is throwing an error saying coib-015

any light towards this

pls get back

thanks

jaya

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Jaya,

Which version of SAP are you working ? If u go through COIB tcode, u will see that after entering the material no and serial no, it shows some serial nos and among that we have to search our entered no and assign that no to the right side window.

In the right side winidow you have to a save -create/change -builit foreground . pls let me know massage no?

Regards,

R.Brahmankar

Former Member
0 Kudos

i am using ver.6.0. when i click the save icon on the right hand side and click on foreground/backgroud this is the error message i am getting.E:COIB:015

Message no. COIB015

i went to se91 to check the description but it has only till 013.

anysuggestions pls help

thanks

Answers (0)