MRP - MTO Question

Hi everyone,

I have a question on managing MTO parts in MRP. Our facility runs a five week production wheel, switching through product families each week. In each family there are a number of make to stock parts and a number of MTO parts. Is it possible for SAP to recognize that if we are running a certain make to stock part (we upload our production schedule, IND Req - VSE) that it should schedule the related MTO (if we have an order for it) to run at that time as well? Basically pair the parts so that if we are running part A (a make to stock part), MRP will schedule part A* as well (an MTO variant of part A).

Thanks for any input,

-Devin

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 05 at 07:07 PM

    Hi Devin

    MRP plans each material separately and it cannot do what you want.

    Regards,

    Caetano