During upgrade testing from 4.7 to 6.0 we found we cannot delete budgeted projects in 6.0. Error messages CJ055 and CJ057 come when we try to delete. Our 4.7 system has different behavior.
In 4.7 a few users are able to delete budgeted projects with no error message. What would allow this? And what would be implication of deleting project with budget?
Thank you
Hi Steve Williams,
Check that WBS is Acct.asst element or not?
If it is Acct.asst element element then we can stop the users.
Hope this clue helps you.
Thanks,
Sanjana.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjana,
WBS is acct assignment. We already use roles and authorizations to control who can delete project. Users with proper role and auth can delete CRTD status project with budget and acct assignment in version 4.7. I am asking how this is possible. What kind of config or authorizations allow user to avoid errors CJ055 and CJ057.
Regards,
Steve
Really doubt if your users managed to delete the WBS inspite of WBS having status BUDG set even in 4.7.
If you wish to delete budgeted WBS elements, first delete the budget on the WBS (using CJ30) and then execute the T Code OPSX (which resets the BUDG status).
Only after performing the above process you'll be allowed to delete the WBS element.
Regards
Sreenivas
Hi Sreenivas,
I also doubted it. So I created project in 4.7, applied budget to it, and saved. System status was then CRTD BUDG. As expected errors CJ055 and CJ057 came when I tried to delete. I then asked one of the projects admins to delete the project. He went directly into CJ02 and deleted the project with no messages, not even the are you sure challenge.
I understand that proper handling is to remove the budget and then delete. But somehow the project admins can delete without removing budget. We are wanting this same functionality in 6.0 but are unable to determine how this is working in 4.7.
Regards
Steve
We now think the reason we can delete projects in BUDG status in 4.72 is because of program error. The note below is for 5.0 and 6.0 systems but we think the program error we have in 4.72 is the same error or closely related.
Note 1071005 - CJ02: Deletion of Project possible with WBS in BUDG status.