Skip to Content

Production Order Confirmation for Labor is posting Incorrect Amounts

When posting a production order confirmation the labor costs is $3,517 when it should be closer to $382.36. I've checked the cost estimates, routings etc. and the system should be charging $382 labor for 2000 units produced. Instead it's charging the production order $3,517. Where can I find the error and provide the solution? I've looked at routings, BOMs and cost estimates but I can't find where the issue is.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers