SES Release Strategy not invoked in Backend from SRM confirmation posting

Hi,

I have configured a SES release strategy based on vendor number in R/3. When a SES is created in R/3 via ML81N the release strategy is invoked as expected. However, when a confirmation is entered in SRM for that vendor, the SES that is created in the backend system is created in accepted status and the release strategy is not invoked.

Can anyone advise how to get this to work the same way as ML81N?

I would expect that the SES would be created in the backend from the confirmation without acceptance and the release procedure to be the same as ML81N.

thanks,

Michelle.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jul 29, 2008 at 07:58 AM

    Hi,

    The SRM confirmation in EBP is the goods receipt(MIGO) and not the service entry sheet entry (ML81N) as we do in Materials management.

    As per my understanding there is no provision of service entry sheet entry in SRM 5.0 as of now and SRM 7.0 has this option coming up :

    In SRM 7.0 ,

    "Supplier-maintained confirmation (service entry sheet) for services performed based on the service items within a purchase order

    Confirmation supporting hierarchical structure of service items"

    are added.

    Look for this information in the thread which speaks about SRM 7.0

    benefits-of-upgrading-to-sap-srm-2007

    which gives the info in slide 11, Delta SRM 7.0, Service procurement -2

    Best regards,

    Sridhar.