Upgrade to SAP PI 7.5 FROM SAP PI 7.1 Dual stack

Mar 05 at 06:42 PM

157

avatar image

Hi Experts,

Currently my client is using SAP Netweaver PI 7.1 dual stack. Only in a single interface he is using ccBPM functionality. He wants to upgrade his system to SAP PI 7.5 using the same licences .

We can use dual stack split procedure for this but for this we need to install AS ABAP and JAVA separately. My query is: -

1) If i redesign the ccBPM interface replacing ccBPM functionality with some other logic would i still require to install AS ABAP as a part of dual stack split procedure?. As all my interfaces can be designed in java stack.

2)Which SAP Netweaver version does i require for SAP PI 7.5?

Regards,

Rajesh Ginka

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Gabriel Cassel
Mar 05 at 07:53 PM
0

Hi Rajesh,

Thank you for contacting us!

Questions:

1) For ccBPM you need the ABAP because of UME and for more things..and is not possible to slip them. Does not have any possibility to split a dual stack in a single stack.

2) SAP Netweaver 7.50 SP 09 and above.

Kind regards,

Gabriel Cassel

SAP Product Support

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Gabriel,

Thanks for the response.

Suppose if my current version of PI(SAP PI 7.1) doesn't have ccBPM, then can i directly upgrade my system to PI 7.5 single stack(java stack) with same licences.

Regards,

Rajesh Ginka