Skip to Content

apo - graphical planning board - order chart

Hi,

in the graphical planning board in apo pp/ds there are different charts. My question refers to the operation chart:

I would like to have empty line between the lines showing the operations. I have mangaed similar structure in the resource view (see pics attached) but I cannot figure out how to do it in the order chart. As you can see there is an empty line between the different resources to increase the visibility. I am looking for the same but in the operation chart.

Thank you for any hint!

best regards,

Pilvi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 01, 2016 at 06:05 PM

    Hi Pilvi,

    I don't know if/how that's possible.

    A way to increase visibility here is to change the font size and font color for the rows, so as to make them bigger.


    Sample Setting

    Results:

    Regards,
    Tiago

    Add comment
    10|10000 characters needed characters exceeded