As per client's requirement, we need to activate mixed costing. Thereby we have to use different production versions in a single month. Therefore based on the production versions different planned orders are required in the system. But during the activity calculation (Transaction KSPP), system is calculating the activity quantity wrong. When there is a single planned order for the entire month, system is calculating the activity quantity correct, but when we use more than one planned order in a single month. System is showing wrong activity quantity at KSPP output.

Please help..

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

avatar image
Former Member Mar 05 at 05:18 AM
0

Is there anybody who could answer this question??